Ready for the New Bulk Electric System Definition?

d-cooper-credit

 

 

 

The North American Electric Reliability Corporation (NERC) and its electric utility industry stakeholders are nearing the effective date of a definition that is critical to the role of NERC and everyone involved in the electric utility industry.  That critical definition is the definition of the Bulk Electric System itself (the BES Definition).  The BES Definition is important because it is used to determine the parts of the North American electric system that are “BES Elements” and critical to reliable operation of that electric system.  Due to the critical nature of the BES Elements, owners of BES Elements are required to comply with all applicable NERC Reliability Standards.  Failure to comply with the Reliability Standards can lead various sanctions, up to and including application of severe fines.

The core of the BES Definition is simple – “…all Transmission Elements operated at 100 kV or higher and Real Power and Reactive Power resources connected at 100 kV or higher. This does not include facilities used in the local distribution of electric energy”.  However, the complexity of the electric system can make application of the BES Definition difficult in some instances.  NERC has addressed that potential difficulty in several ways – first by adding to the BES Definition a list of Inclusions (classes of facilities automatically considered BES Elements) and Exclusions (classes of facilities automatically not considered BES Elements).  NERC and its stakeholders have also developed several guides and held a series of seminars to help asset owners in determining whether facilities are or aren’t BES Elements.  The guides and documents from seminars are publicly available on the NERC website.  The general BES definition site is here, while the seminar presentations are available here.

Further, in line with FERC direction, NERC has also developed a detailed Exception Process where facility owners and certain other entities involved in the reliability of the BES can request that a specific facilities that is not a BES Element under the BES Definition be changed registered as a BES Element.  The facility owner can also request the opposite – that a facility that is a BES Element under the BES Definition be removed from the list of BES Elements.

A recurring comment from FERC concerning the BES Definition was that the new definition should not result in significant registration or de-registration of BES Elements.  Regardless, all owners of electric facilities are required to perform a self-evaluation, using NERC’s hierarchical process, to develop a list of owned BES Elements.   The asset owners are then to register the results of their self-evaluation through a new web-based tool sponsored by NERC called “BESNet”.  Registration for BESNet began in May, 2014.  The tool is scheduled to “go live” on July 1, 2014.  While NERC allowed a period of 24 months after July 1 to come into compliance with the new BES Definition, all asset owners should perform their individual BES Element self-evaluation as soon as possible and enter the results into BESNet.  That way, if there is any disagreement on the BES Element status for any items on the owner’s list, there will be time to hold discussions with the asset owner and affected reliability entities and, if necessary, file an Exception Request well before the compliance deadline.

Legal Disclaimer

Please note that the materials contained within this web site have been prepared by Jennings, Strouss & Salmon, P.L.C. for informational purposes only so that readers may learn more about the firm, the services it provides the background of its attorneys, and recent developments in the law. These materials do not constitute, and should not be considered, legal advice, and you are urged to consult with an attorney on your own specific legal matters. Transmission of the information contained in the Jennings, Strouss & Salmon web site is not intended to create, and receipt by the reader does not constitute, an attorney-client relationship with Jennings, Strouss & Salmon or any of its individual attorneys. While we would certainly like to hear from you, we cannot represent you until we know that doing so will not create a conflict of interest. Please do not send us any information about a matter that may involve you until you receive written authorization to do so from one of our attorneys. Unless otherwise indicated in individual attorney biographies, attorneys resident in the firm's various offices are not certified by the Board of Legal Specialization or a similar body of any State. This site may contain hyperlinks to Web sites operated by parties' independent from Jennings, Strouss & Salmon. Such hyperlinks are provided for your reference only. Jennings, Strouss & Salmon does not control such Web sites, and is not responsible for their content. Jennings, Strouss & Salmon's inclusion of hyperlinks to such Web sites does not imply any endorsement of the material on such Web sites or any association with their content. Your access and use of such sites, including information, material, products, and services therein, shall be solely at your own risk. Further, because the privacy policy of this Site is applicable only when you are on this Site, once linked to another Web site, you should read that site's privacy policy before disclosing any personal information.